Question 11
Choose 1
Sprint 1 of 5 has been completed in a Sales Cloud implementation. The business analyst (BA) met with the stakeholders to prioritize the backlog for the next sprint. One of the stakeholders wants to include a medium-priority item. There is still a list of high-priority items that need to be addressed.
How should the BA communicate with the stakeholder?
Correct answer:
B. Q Verify why the item is medium-priority, explain the reason, and determine if the item
priority was misjudged compared to other items.
Explanation
In an Agile framework, the backlog is dynamic, but priority is the primary driver for what gets worked on next. The BA's role is to facilitate collaboration and ensure the team is always working on the most valuable items. Option B demonstrates this perfectly: it starts with a collaborative inquiry ("Verify why..."), promotes transparency ("explain the reason" referring to the existing high-priority items), and leads to a joint re-evaluation ("determine if the item priority was misjudged"). This approach respects the stakeholder's input while upholding the agreed-upon prioritization framework for the good of the project.
Why A is incorrect:
While collaboration is key, scheduling a meeting to re-evaluate all items is an inefficient use of time for the entire team. The current priorities were likely already established with stakeholder input. A full re-prioritization meeting should be a last resort, not the first response to a single request.
Why C is incorrect:
This is a failure of the BA's responsibility to the project's goals. Automatically promoting a medium-priority item over high-priority items without justification undermines the prioritization process, delays higher-value features, and sets a bad precedent for future sprints. It could lead to scope creep and project failure.
Reference/Key Concept:
This question tests the BA's skills in Backlog Management and Stakeholder Communication within an Agile methodology. The BA must act as a facilitator, balancing stakeholder desires with the project's priorities and goals. The core principle is to maximize the value of the work delivered in each sprint, which is guided by a properly prioritized backlog.
In an Agile framework, the backlog is dynamic, but priority is the primary driver for what gets worked on next. The BA's role is to facilitate collaboration and ensure the team is always working on the most valuable items. Option B demonstrates this perfectly: it starts with a collaborative inquiry ("Verify why..."), promotes transparency ("explain the reason" referring to the existing high-priority items), and leads to a joint re-evaluation ("determine if the item priority was misjudged"). This approach respects the stakeholder's input while upholding the agreed-upon prioritization framework for the good of the project.
Why A is incorrect:
While collaboration is key, scheduling a meeting to re-evaluate all items is an inefficient use of time for the entire team. The current priorities were likely already established with stakeholder input. A full re-prioritization meeting should be a last resort, not the first response to a single request.
Why C is incorrect:
This is a failure of the BA's responsibility to the project's goals. Automatically promoting a medium-priority item over high-priority items without justification undermines the prioritization process, delays higher-value features, and sets a bad precedent for future sprints. It could lead to scope creep and project failure.
Reference/Key Concept:
This question tests the BA's skills in Backlog Management and Stakeholder Communication within an Agile methodology. The BA must act as a facilitator, balancing stakeholder desires with the project's priorities and goals. The core principle is to maximize the value of the work delivered in each sprint, which is guided by a properly prioritized backlog.